NOTICE OF FINAL PAYMENT
Pursuant to Wyoming Statutes, notice is hereby given that the City of Powell, Wyoming has accepted the work on the Vining Substation project as substantially completed according to the plans and specifications and rules set forth in the Contract and that HDR, Inc. is entitled to final settlement there- fore. Upon the 41st day (June 27th, 2022) after the first publication of this notice, the City of Powell, Wyoming, under whose direction or supervision the work has been carried out, will pay to HDR, Inc. the full amount due under the Contract. This section does not relieve HDR, Inc. and the sureties on its bond from any claims or work or labor done, or materials or supplies furnished in the execution of the Contract.
First Publ., Tues., May 17, 2022