Abatement bids

Posted

Northwest College in Powell, Wyoming is seeking bids from qualified asbestos abatement contractors for their asbestos abatement project at the DeWitt Student Center Building. The work will include, but is not limited to, the removal and proper disposal of the following asbestos-containing materials: floor tile and mastic, floor tile and mastic under carpet, residual mastic under carpet, 3” vinyl cove base and mastic, acoustical ceiling plaster/texture, white woven HVAC collars, and mudded pipe fitting insulation.
The asbestos abatement time frame, including final air clearance monitoring and removal of containment barriers, is: from December 19, 2022 to February 17, 2023.
Sealed bids will be received until 2:00 PM on September 6, 2022 in the office of the Mr. Dennis Quillen, Interim Facilities Director, Northwest College Physical Plant located at Road 9 ½, Powell, Wyoming 82435 for: Pre-Demolition Asbestos Abatement, DeWitt Student Center Building, Powell, Wyoming.
A mandatory pre-bid meeting and walk through will be held on August 16, 2022 at 11:00 AM. Interested contractors shall meet at the Physical Plant Building for the pre-bid meeting prior to the walk through at the DeWitt Student Center Building. If you have any questions regarding this project, you may contact Robert Brownell of Northern Industrial Hygiene at (406) 671-2090 or Mark Oliver of Northern Industrial Hygiene at (406) 670-5581.
Bids shall be submitted on forms provided with the Contract Documents. Contract Documents, Plans & Specifications shall be available on or after August 8, 2022, at the Northern Industrial Hygiene Office (406-245-7766) or at the mandatory pre-bid meeting and walk through.
A Bid Bond of 10% of the project price will be required.
Bids will be accepted for ONE GENERAL CONTRACT.
The contract shall be let to the responsible certified resident making the lowest bid if the certified resident’s bid is not more than five percent (5%) higher than that of the lowest responsible nonresident bidder.
If a nonresident contractor is selected, they must follow Wyoming regulations regarding preference for Wyoming laborers.
The Contractor shall comply with all fair labor practices and Wyoming statutes.
No bidder may withdraw his/her bid for thirty (30) days after the scheduled time for receipt of bids, except as noted in the Instructions to Bidders.
The Owner reserves the right to reject any and all bids and to waive any informalities or irregularities in any bid received.
Dennis Quillen, Interim Facilities Director, Northwest College, Powell, Wyoming.
First Publ., Thurs., Aug. 4, 2022
Final Publ., Thurs., Aug. 11, 2022

Comments